Actions
Bug #537
openVerify that an employee can apply for the remaining half-day leave on the same date
Start date:
08/13/2026
Due date:
% Done:
0%
Estimated time:
Platform:
Web
Description
| Field | Details |
|---|---|
| Test Case ID | TC_LEAVE_001 |
| Module | Leave Management |
| Test Scenario | Verify that an employee can apply for the remaining half-day leave on the same date |
| Precondition | Employee has sufficient leave balance and has already applied for First Half leave |
| Test Data | Leave Date: 13/08/2026; First Half already applied |
| Steps | 1. Navigate to My Leave. 2. Click Apply Leave. 3. Select the required Leave Type. 4. Select 13/08/2026 as the Start Date and End Date. 5. Select Second Half as the Start Date Breakdown. 6. Verify the Total Days. 7. Click Submit. |
| Expected Result | System should allow the employee to apply for the Second Half on the same date without displaying the overlap validation message. Total leave for the date should be 1.0 day. |
| Priority | High |
| Type | Functional |